What Is Earned Value? Meaning, Formulas and a Project Example

For project managers, PMO leads and contractors: tell whether a project is ahead or behind, over or under budget, with one consistent set of numbers.

A project manager and site supervisor checking progress on an office fit-out

What is earned value? Earned value (EV) is the budgeted cost of the work actually completed on a project. It lets you compare what you planned to spend, what you have spent, and what that spending has achieved, all in rupees.

Most project reports show only two of those three. A project that has spent half its budget may look fine, until you find it has finished only a third of the work.

This page explains the terms and formulas, works through the numbers, shows an illustrative project, and describes how Apragya calculates earned value from project data.

Earned value meaning and formulas

Earned value management uses three numbers. Planned value (PV) is the budgeted cost of the work scheduled to date. Earned value (EV) is the budgeted cost of the work actually done. Actual cost (AC) is what has been spent. Budget at completion (BAC) is the total budget.

From these come the indices. Cost variance is EV minus AC, and schedule variance is EV minus PV. The cost performance index (CPI) is EV divided by AC, and the schedule performance index (SPI) is EV divided by PV. A simple estimate at completion (EAC) is BAC divided by CPI.

A worked example: a project with a BAC of INR 10 lakh is 40% complete, so EV is INR 4 lakh. Planned value to date is INR 5 lakh and actual cost is INR 4.5 lakh. CPI is 4 divided by 4.5, or 0.89. SPI is 4 divided by 5, or 0.8. EAC is 10 divided by 0.89, about INR 11.25 lakh.

  1. Set the budget at completion.
  2. Work out planned value to date from the schedule.
  3. Work out earned value from work completed.
  4. Take actual cost from time and expenses.
  5. Calculate CPI, SPI and EAC.

An example: an interior fit-out in Bengaluru

Take an illustrative fit-out contractor with a budget of INR 50 lakh for an office floor over ten weeks. At the end of week four the site manager reports good progress.

Week four earned value snapshot

  1. The approved budget for the fit-out.

  2. Work that should be done by week four.

  3. Budgeted cost of the work actually done.

  4. What has been spent so far.

  5. Both below 1: over cost and behind plan.

  6. Budget divided by CPI.

The site looked busy, but the numbers showed a project heading 12.5 lakh over budget.

Seeing a forecast of INR 62.5 lakh at week four, the contractor re-sequenced the false ceiling and electrical work, stopped paying for idle labour, and raised a change request for extra partitions the client had asked for. The overrun was smaller than forecast, and the client knew why.

A balance scale weighing building materials against a heavier pile of coins
At week four, the money spent outweighed the work done, and the contractor re-planned early.

How earned value management works in Apragya

Step 1 of 5

Budget and costs

Project budgets, time logs and expenses give the planned and actual cost.

  1. Budget and costs: Project budgets, time logs and expenses give the planned and actual cost.
  2. Progress: Task completion gives the share of work done.
  3. EVM snapshot: BAC, PV, EV, AC, CPI, SPI, cost and schedule variance, and EAC for each project.
  4. Trend: See how CPI and SPI move over time, not just today's value.
  5. AI forecast: An AI forecast reads the trend and explains what it means, for the manager to review.

CPI and SPI formula, read the right way

A CPI of 0.8 means every rupee spent buys 80 paise of planned work. An SPI of 0.8 means the project has done 80% of the work it should have done by now. Neither number means much once, and both mean a lot as a trend.

Earned value in a spreadsheet, against Apragya

FeatureSpreadsheet EVMApragya Projects
Actual costCollected from accountsTime logs and expenses on the project
ProgressEstimated in a meetingFrom task completion
IndicesFormula per projectCPI, SPI and EAC calculated
TrendCopied week to weekTrend kept for each project
ExplanationWritten by the managerAI forecast, reviewed by the manager

Checked against public information on 16 September 2026.

What happens without earned value

Late cost surprises

Overruns show up at the last milestone, when little can be done.

Schedule optimism

Percent complete is guessed, and every task sits at 90% for weeks.

Hard conversations

Clients hear about a slip after it has happened, not before.

No common measure

Each project reports progress in its own way.

What sets Apragya apart for project control

One project record

Tasks, time, costs, risks and change requests together.

Change requests

Scope changes are recorded, so the budget moves with them.

Milestones

Progress and billing milestones on the same project.

Multi-company

Projects belong to the right company in a group.

Access by role

Clients, members and managers see what they should.

Early warning

Agents can be set to flag projects whose indices slip.

See project financials, time logs, change requests and the AI agent for project delay prediction.

Getting started with earned value analysis

  1. Set a budget and a schedule for the project.
  2. Break the work into tasks you can mark complete.
  3. Log time and expenses against the project.
  4. Read CPI and SPI every week.
  5. Act when either stays below 1 for two weeks.

Start with one project; the habit matters more than the precision.

What it costs to start

INR 7,999
Pro, a month
Up to 25 users, with Project Management and every enterprise app
5,000
AI Credits a month
Included on Pro
Free
Up to 3 users
CRM and HR, to try the platform first

Earned value analysis example questions, answered

Is earned value only for large projects?
No. Any project with a budget and a task list can use it. Smaller projects simply review it less often.
How is percent complete measured?
It should come from work finished, not from time spent. Many teams use task completion or milestones.
What is a good CPI?
A CPI of 1 or above means the work is costing what was planned or less. Below 1 means the project is over cost.
Does the AI forecast change the numbers?
No. It reads the EVM figures and trend and explains them. The manager decides what to do.
What does it cost to start?
Project Management comes with the Pro plan, INR 7,999 a month for up to 25 users, which includes every enterprise app, 5,000 AI Credits a month, single sign-on and audit logs. The free plan covers up to 3 users with CRM, HR and Vendor Onboarding if you want to try the platform first.

Know where each project really stands

Set a budget, log time and costs, and read CPI and SPI every week.