What Is Earned Value? Meaning, Formulas and a Project Example
For project managers, PMO leads and contractors: tell whether a project is ahead or behind, over or under budget, with one consistent set of numbers.
What is earned value? Earned value (EV) is the budgeted cost of the work actually completed on a project. It lets you compare what you planned to spend, what you have spent, and what that spending has achieved, all in rupees.
Most project reports show only two of those three. A project that has spent half its budget may look fine, until you find it has finished only a third of the work.
This page explains the terms and formulas, works through the numbers, shows an illustrative project, and describes how Apragya calculates earned value from project data.
Earned value meaning and formulas
Earned value management uses three numbers. Planned value (PV) is the budgeted cost of the work scheduled to date. Earned value (EV) is the budgeted cost of the work actually done. Actual cost (AC) is what has been spent. Budget at completion (BAC) is the total budget.
From these come the indices. Cost variance is EV minus AC, and schedule variance is EV minus PV. The cost performance index (CPI) is EV divided by AC, and the schedule performance index (SPI) is EV divided by PV. A simple estimate at completion (EAC) is BAC divided by CPI.
A worked example: a project with a BAC of INR 10 lakh is 40% complete, so EV is INR 4 lakh. Planned value to date is INR 5 lakh and actual cost is INR 4.5 lakh. CPI is 4 divided by 4.5, or 0.89. SPI is 4 divided by 5, or 0.8. EAC is 10 divided by 0.89, about INR 11.25 lakh.
- Set the budget at completion.
- Work out planned value to date from the schedule.
- Work out earned value from work completed.
- Take actual cost from time and expenses.
- Calculate CPI, SPI and EAC.
An example: an interior fit-out in Bengaluru
Take an illustrative fit-out contractor with a budget of INR 50 lakh for an office floor over ten weeks. At the end of week four the site manager reports good progress.
Week four earned value snapshot
The approved budget for the fit-out.
Work that should be done by week four.
Budgeted cost of the work actually done.
What has been spent so far.
Both below 1: over cost and behind plan.
Budget divided by CPI.
Seeing a forecast of INR 62.5 lakh at week four, the contractor re-sequenced the false ceiling and electrical work, stopped paying for idle labour, and raised a change request for extra partitions the client had asked for. The overrun was smaller than forecast, and the client knew why.
How earned value management works in Apragya
Step 1 of 5
Budget and costs
Project budgets, time logs and expenses give the planned and actual cost.
- Budget and costs: Project budgets, time logs and expenses give the planned and actual cost.
- Progress: Task completion gives the share of work done.
- EVM snapshot: BAC, PV, EV, AC, CPI, SPI, cost and schedule variance, and EAC for each project.
- Trend: See how CPI and SPI move over time, not just today's value.
- AI forecast: An AI forecast reads the trend and explains what it means, for the manager to review.
CPI and SPI formula, read the right way
A CPI of 0.8 means every rupee spent buys 80 paise of planned work. An SPI of 0.8 means the project has done 80% of the work it should have done by now. Neither number means much once, and both mean a lot as a trend.
Earned value in a spreadsheet, against Apragya
| Feature | Spreadsheet EVM | Apragya Projects |
|---|---|---|
| Actual cost | Collected from accounts | Time logs and expenses on the project |
| Progress | Estimated in a meeting | From task completion |
| Indices | Formula per project | CPI, SPI and EAC calculated |
| Trend | Copied week to week | Trend kept for each project |
| Explanation | Written by the manager | AI forecast, reviewed by the manager |
Checked against public information on 16 September 2026.
What happens without earned value
Late cost surprises
Overruns show up at the last milestone, when little can be done.
Schedule optimism
Percent complete is guessed, and every task sits at 90% for weeks.
Hard conversations
Clients hear about a slip after it has happened, not before.
No common measure
Each project reports progress in its own way.
What sets Apragya apart for project control
One project record
Tasks, time, costs, risks and change requests together.
Change requests
Scope changes are recorded, so the budget moves with them.
Milestones
Progress and billing milestones on the same project.
Multi-company
Projects belong to the right company in a group.
Access by role
Clients, members and managers see what they should.
Early warning
Agents can be set to flag projects whose indices slip.
See project financials, time logs, change requests and the AI agent for project delay prediction.
Getting started with earned value analysis
- Set a budget and a schedule for the project.
- Break the work into tasks you can mark complete.
- Log time and expenses against the project.
- Read CPI and SPI every week.
- Act when either stays below 1 for two weeks.
Start with one project; the habit matters more than the precision.
What it costs to start
Earned value analysis example questions, answered
Is earned value only for large projects?
How is percent complete measured?
What is a good CPI?
Does the AI forecast change the numbers?
What does it cost to start?